Residential and commercial building Allersberg
Successful renovation and new construction in the middle of the marketplace. The house consists of four residential units and one commercial unit.
The entire building is heated exclusively with the KS-QUARO THERM wall temperature control system, a complete system for temperature control of wall surfaces. In winter it creates comfortable warmth and in summer it provides cooling.
Building owner
Wohn u. Gewerbebau, Allersberg
Finalization
2013
Heating demand
41,9 kWh/m²a
Architecture
Specialist planning
Zapf Daigfuss Vertriebs-GmbH
(Text source: KS-Quadro Bausystem GmbH; Zapf Daigfuss)
Other interesting projects from the category Thermal Activated Building– Efficient heating & cooling & Renovation
Pediatric practice and apartments
The architects ad2 from Weiden am See in Burgenland prefer to work with concrete. At the pediatric practice of Dr. Langer in Perchtoldsdorf, south of ...
Der Stadtelefant
A new Gründerzeit - there is more building going on in Vienna than there has been in a long time. From the synergies of three architectural firms acti...
Expansion of the Plattenalm in Krimml
At the Plattenalm in Krimml, a new building is being constructed as an extension for gastronomy, staff housing, and a snow groomer garage. In total, 3...
Redevelopment residential building Große Neugasse
For the non-profit developer Sozialbau, the refurbishment of its existing buildings is an important concern. The use of the facade to increase energy ...
Fiegl&Spielberger
The ultra-modern, two-story building with a total floor space of 1,700 m² has created a lively showroom featuring all the company's services....
Villendorf - Ensemble am Steindl
At Bäckerberggasse 12, seven villas are being built with a total of 62 condominiums offering a unique view of the Danube and Göttweig Abbey. In additi...
Südpack
After a construction period of only two years and with a total investment of 40 million euros, a two-story production and storage hall, a four-story o...
New building criminal justice center
On the site at the southern Oberwiesenfeld / Leonrodplatz in Munich, a multi-storey building with three inner courtyards was created, in which all are...
BORG Oberndorf
A spacious school courtyard, which continues into the inner courtyard of the school, creates a striking and clear access situation to the school build...
Alnatura Campus
For the 55,000 square metre Alnatura Campus, the former barracks site in the southwest of Darmstadt was extensively renaturalised. Sealed areas were b...